Proof of concept ”Work like” prototypes using development kits
Early customer feedback

Prove Core Technologies
2 - 3 months
Engineering samples using rapid prototyping, 10 - 50 pcs
Customer Beta testing
Pre-compliance testing
Second iteration, if needed
EVT

Engineering Samples Meet Specs
5 - 6 months
Tooling for Mechanical parts CM does product prototyping using tooling, 50- 100 units
Compliance tests (FCC, UL, CE)
Deliver samples to beta testers
DVT

Pre-Production Samples Ready
4 - 5 months
Setup manufacturing process CM applies mass-production techniques, 500 - 1000+ units
Final compliance tests
Deliver product to early backers
PVT

Production Process Validated
3 - 4 months